The sprint
Read the brief and the spread of cards by topic, then press Start. The clock bar stays pinned to the top of the screen, and you can change any pick until you press Finish the sprint.
Practice cards here are written for study, not taken from PMI. The real CAPM mixes multiple choice with drag-and-drop, hot spot, comic-strip and video items.
Sprint not started
Sprint rules
- This sprint: 60 cards, 72 minutes on the clock.
- No verdicts while the clock runs. Picks can be changed until you finish.
- Time-out ends the sprint and scores what you picked. Unpicked cards count as misses.
- The result is a raw percentage and a topic table. It is not a pass or fail line, because none is published for this sprint.
The real CAPM exam, per PMI CAPM Examination Content Outline, 2023 update (checked October 30, 2026): 180 minutes, 150 questions. Of those, 135 are scored and 15 are unscored pretest items. PMI reports pass or fail with a rating for each domain and does not publish a passing score.
To do 0
Doing
Picked 0
Preview the first ten cards, answers included
Card 01 of 60Life cycles & portfolios
A medical device program must satisfy fixed regulatory submission requirements and pass scheduled audits, yet the product’s user interface requirements are highly uncertain and will evolve through customer trials. The sponsor asks how the delivery approach should be structured and documented. What is the best response?
Best answer: D.
Note on A
A fully predictive plan fits the audit trail but forces fixed requirements onto an interface that the team expects to discover through customer trials.
Note on B
Running everything as agile with reviews at sprint end does not guarantee the fixed submission baselines and gate evidence that regulators expect.
Note on C
Adding checkpoints only on request leaves compliance to chance; regulatory gates need to be planned from the start, not bolted on later.
Note on D
Correct: A hybrid approach lets stable compliance work follow predictive gates while the uncertain interface evolves iteratively, and the plan states which parts use which approach.
Card 02 of 60Plans & registers
A project’s final deliverable was formally accepted by the customer yesterday. Which activity should the project manager perform NEXT as part of closing the project?
Best answer: D.
Note on A
The scope baseline is not rewritten after acceptance to match the result; changes should have gone through change control earlier.
Note on B
Validating scope is the step that produces formal acceptance, and the customer has already accepted the deliverable.
Note on C
Quality inspection happens before the deliverable is presented for acceptance, so it is already behind the project at this point.
Note on D
Correct: Once the deliverable is accepted, closing work turns to finalizing lessons learned and archiving project records for the organization.
Card 03 of 60Risks & issues
A project manager discovers that a key supplier will miss a delivery date, putting a milestone at risk. Without collecting the delivery records, cost impact, or alternative sourcing options, the project manager forwards a short message to the sponsor demanding immediate intervention. What is the primary problem with this action?
Best answer: D.
Note on A
Thresholds matter, but going to the sponsor about a milestone risk may well be within them; the real gap is the missing evidence.
Note on B
Nothing in the action asks the sponsor to update the risk register, and register upkeep stays with the project team.
Note on C
How fast a sponsor responds is speculation and is not what makes this escalation weak.
Note on D
Correct: An escalation should carry the facts, the impact, and possible responses so the sponsor can decide; a bare demand gives them nothing to act on.
Card 04 of 60Roles & leadership
A supportive and influential stakeholder who is not authorized to view contract pricing requests the confidential cost breakdown for a deliverable. What should the project manager do?
Best answer: C.
Note on A
Asking for discretion does not change the fact that the stakeholder is not authorized to see the pricing.
Note on B
Stalling avoids the question without being honest about why, which damages trust and leaves the request unresolved.
Note on C
Correct: The project manager respects the confidentiality obligation and is transparent about the reason, which protects both the contract and the relationship.
Note on D
Even a trimmed version of restricted data can breach the agreement, and the motive here is avoiding conflict rather than honoring the obligation.
Card 05 of 60Meetings & problem solving
At the end of a planning meeting, the facilitator asks each team member to show zero to five fingers to indicate their level of support for the plan. Which technique is this?
Best answer: D.
Note on A
Planning poker is an estimation technique in which team members reveal cards with relative size values, not a measure of support for a plan.
Note on B
Dot voting distributes a limited number of dots across options to prioritize them, rather than signaling agreement levels.
Note on C
Roman voting uses a simple thumbs up, sideways, or down, so it offers three positions instead of a zero-to-five scale.
Note on D
Correct: Fist of five asks each person to show zero to five fingers, giving a quick read of how strongly the group supports a decision.
Card 06 of 60Predictive processes
During testing, a software team finds recurring coding defects. The sponsor asks for a document that summarizes the quality issues, recommends corrective actions, and suggests process improvements. Which document should the project manager provide?
Best answer: B.
Note on A
An issue log tracks individual problems, owners, and due dates; it does not summarize quality findings or recommend process improvements.
Note on B
Correct: A quality report summarizes quality issues and findings and recommends corrective actions and process improvements.
Note on C
A status report covers overall progress on scope, schedule, and cost, so quality analysis would be only a small part of it at most.
Note on D
A risk report describes overall risk exposure and individual risks, not defects that have already been found.
Card 07 of 60WBS & critical path
A project manager decides to fast-track two sequential activities that have a mandatory finish-to-start dependency, overlapping the last three days of the first activity with the first three days of the second. The second activity depends on design output produced by the first. What is the primary risk introduced by this decision?
Best answer: C.
Note on A
Morale can suffer under pressure, but this overlap does not add hours or workload by itself, so morale is not the primary risk.
Note on B
Fast-tracking changes the working schedule, but the baseline only changes through approved change control, not because two activities overlap.
Note on C
Correct: Starting the dependent activity before the design it needs is complete risks rework when that design changes or turns out different than assumed.
Note on D
Adding resources to activities is crashing; fast-tracking overlaps work in parallel and does not by definition add labor cost.
Card 08 of 60Cost & schedule variance
A work package is 40 percent complete, and its baseline budget (Budget at Completion) is $750,000. Using EV = percent complete × BAC, what is the earned value?
Best answer: A.
Note on A
Correct: Earned value is 0.40 × $750,000 = $300,000, the budgeted value of the work actually completed.
Note on B
This divides the budget by the percent complete instead of multiplying by it, which gives a figure larger than the whole budget.
Note on C
This value comes from multiplying by 25 percent rather than by the stated 40 percent complete.
Note on D
This is the budgeted value of the remaining 60 percent of the work, not the earned value of what is done.
Card 09 of 60Agile fit & frameworks
A product is delivered by six Scrum teams located across three continents in different time zones. Leadership notices that scaling has introduced new difficulties compared with a single co-located team. Which challenge is most characteristic of this distributed scaling situation?
Best answer: C.
Note on A
Distributed teams need more synchronization, not less, so removing shared events would make integration problems worse.
Note on B
Each team keeps its own daily meeting at scale; preventing it is neither a goal nor a typical difficulty.
Note on C
Correct: Teams spread across time zones struggle to keep a common cadence and coordinate dependencies, which is the defining challenge of distributed scaling.
Note on D
Velocity is a team-specific planning measure, and forcing one uniform metric across teams is a misuse rather than an inherent scaling challenge.
Card 10 of 60Iterations & backlog
A business analyst on an agile team notices significant technical debt accumulating. Believing this poses a critical risk to future scalability, the BA moves several refactoring tasks to the top of the upcoming sprint backlog. During the sprint review, the product owner is frustrated that requested market-facing features were not delivered. What should the business analyst have done differently to prevent this dispute?
Best answer: C.
Note on A
Stopping the iteration until the debt is gone is an overreaction, and a committee does not own the team’s backlog.
Note on B
Sizing input from the technical lead does not address the real conflict, which is who decides the order of the backlog.
Note on C
Correct: The product owner orders the backlog, so the business analyst should raise the technical debt risk with them and agree on its priority against market features.
Note on D
Agile iterations are not controlled through a change control board; priority changes are negotiated with the product owner in the backlog.
The sprint next to the real sitting
| Point | This sprint | The CAPM exam |
|---|---|---|
| Clock | 1.2 minutes per card, in one sitting | 3 hours (180 minutes); the optional tutorial and survey are not counted |
| Length | shown in the brief above the Start button | 150 in total, of which 15 are unscored pretest items placed at random; see the questions and time page |
| Break | none | one 10-minute break once you have answered and reviewed the first 75; those stay locked afterward |
| Item types | multiple choice, one best answer | multiple choice, drag-and-drop matching, hot spot, animations and comic strips; online candidates see comic strips but no animations |
| Result | raw score and a table by topic | pass or fail, with a performance rating for each of the four domains |
After the clock stops
Read the topic table before the percentage. A raw score moves from one day to the next; a topic that sits well below your overall rate twice in a row does not, and its row links straight to that topic’s page in the CAPM study guide.
Then open Review every card. Each card shows its key with a note under every option, so the cards you got right by elimination get a second look as well. Run the sprint again only after you have worked the weak topics on the untimed CAPM practice test; a rerun straight away mostly measures your memory of the last one.
Before you press Start
Is this a CAPM exam simulator?
It simulates the clock, the mixed order and the silence while you work. It does not reproduce PMI’s test software or its drag-and-drop and hot spot items, and it is shorter than the three-hour sitting (CAPM content outline, checked October 30, 2026).
Why 1.2 minutes per card?
Three hours divided across the full CAPM comes to 1.2 minutes an item (CAPM content outline, checked October 30, 2026). The sprint keeps that pace so the clock pressure feels the same, even though the set is shorter.
What score should I aim for?
There is no number to aim at that PMI would recognize. PMI sets the CAPM passing standard by psychometric analysis and does not publish it (PMI Certification Handbook, checked October 30, 2026), so treat the topic table as the signal. The CAPM passing score page covers what the score report does show.