How the board works
The board borrows its layout from a kanban wall. Cards wait in To do, one sits in Doing while you answer it, and answered cards move to Done, tinted as right or missed. The arrow keys step back and forward, and the keys 1 to 6 or A to F pick an option.
The topic chips above the board narrow it to one lane. A chip is also a link you can keep: the earned value lane opens with cost and schedule variance already selected, and the requirements lane does the same for elicitation and traceability.
Every card has a single best answer, and on a CAPM-style card more than one option often sounds reasonable. That is why the notes cover the losing options too: each says where that option falls short of the key.
The board
Work down the To do column or pick a chip first. Finish the board opens your score, a table by topic and a jump to your first miss.
Practice cards here are written for study, not taken from PMI. The real CAPM mixes multiple choice with drag-and-drop, hot spot, comic-strip and video items.
Card 01 of 45 · 0 done · 0 right
To do 45
Doing
Card 01 of 45Life cycles & portfolios
A digital marketing team is building a customer portal. Requirements are expected to change as users test early releases, and the sponsor wants frequent demonstrations and rapid incorporation of feedback. Speed of learning matters more than predicting the final scope. Which planning approach best fits this project?
Note on A
Defining every requirement up front assumes stable scope, but here requirements are expected to change as users test early releases.
Note on B
A detailed baselined WBS with formal change control suits predictable scope and would slow the rapid feedback loop the sponsor wants.
Note on C
Phase gates add approval stops between releases, which delays learning when frequent demonstrations are the goal.
Note on D
Correct: High uncertainty calls for adaptive planning: the team orders the backlog by value and delivers short iterations so feedback shapes the next increment.
Card 02 of 45Plans & registers
At closure, the sponsor asks for a summary of how the project performed against its scope, schedule, cost and quality objectives and whether it met the business need. Which document provides this?
Note on A
Correct: The final report summarizes how the project performed against its scope, schedule, cost and quality objectives and whether it met the business need.
Note on B
The benefits management plan describes how and when benefits will be measured; it is a plan, not an end-of-project performance summary.
Note on C
Work performance reports show status during the project to support decisions; they are not the closing summary the sponsor is asking for.
Note on D
The lessons learned register captures what worked and what did not for future use, not a verdict on performance against objectives.
Card 03 of 45Risks & issues
While integrating the subsidiary plans, the project manager notices the schedule assumes staff will work during a planned plant shutdown. What should the project manager do?
Note on A
The project manager owns plan integration; a clear factual conflict like this does not need the sponsor to pick a winner.
Note on B
The shutdown is a known fact, not an uncertain event, so treating it as a risk leaves an unworkable schedule in place.
Note on C
Approving a plan with a known conflict pushes a predictable problem into execution, where it costs more to fix.
Note on D
Correct: Integrating subsidiary plans means making them consistent, so the project manager resolves the conflict and updates every affected plan.
Card 04 of 45Roles & leadership
During final product validation, a project manager discovers a severe safety defect that could cause physical harm to end-users. The functional manager explicitly orders the project manager to ignore the defect and proceed with the release, citing critical quarterly financial goals. What is the mandatory next step for the project manager?
Note on A
Fixing the defect secretly bypasses transparency and governance, and stakeholders still need to know about a safety issue.
Note on B
A disclaimer does not remove a known risk of physical harm; releasing anyway still puts users in danger.
Note on C
Correct: Safety and honesty come first, so the project manager raises the defect through the organization’s governance and escalation channels instead of following an unsafe directive.
Note on D
Following a directive that puts users at risk conflicts with the project manager’s duty to act ethically and protect people.
Card 05 of 45Meetings & problem solving
During a brainstorming session to identify risks, a senior stakeholder starts evaluating and rejecting ideas as they are raised. What should the facilitator do?
Note on A
Voting on each idea as it is raised turns generation into evaluation and discourages people from offering more risks.
Note on B
Letting a senior person judge ideas on the spot suppresses contributions, especially from less senior participants.
Note on C
Formal analysis comes after identification; switching now cuts off the search for risks before the list is complete.
Note on D
Correct: Brainstorming separates generating ideas from judging them, so the facilitator holds evaluation until the idea list is complete.
Card 06 of 45Predictive processes
A project needs 500 standard laptops with a fully defined specification, and price will be the main selection criterion. Which procurement document should be sent to sellers?
Note on A
A letter of intent signals an intention to contract with a chosen seller; it does not ask sellers for prices.
Note on B
A request for proposal suits complex needs where sellers propose solutions, which is more than this fully specified purchase requires.
Note on C
A request for information gathers knowledge about seller capabilities, which is not needed when the specification is already defined.
Note on D
Correct: When the item is standard and fully specified and price drives selection, a request for quotation asks sellers for prices.
Card 07 of 45WBS & critical path
A project manager must compress the schedule by three weeks to meet a regulatory deadline. The team has identified several candidate activities, some on the critical path and some with float. Which sequence of actions best reflects sound compression decision-making?
Note on A
Correct: Compression starts by confirming which activities are on the critical path, then weighs rework risk and cost-time trade-offs before crashing the cheapest critical activities.
Note on B
Skipping the critical-path check risks spending money on activities that have float and will not shorten the project.
Note on C
Crashing before confirming the critical path and the rework risk can waste money on activities that do not move the finish date.
Note on D
Crashing before confirming the critical path means the cheapest activities chosen may not shorten the schedule at all.
Card 08 of 45Cost & schedule variance
A project manager tells the sponsor that the project is performing better than planned because it has spent only $450,000 of its $600,000 budget. The project’s earned value is $380,000 and its planned value is $420,000. What is the flaw in the manager’s conclusion?
Note on A
No performance index or forecast is applied here; the manager simply compares spending with the total budget.
Note on B
Correct: Spending less than the budget says nothing about progress; earned value of $380,000 against $450,000 spent gives a CPI below 1, so the project is over budget for the work done.
Note on C
The manager makes a cost claim, not a schedule claim, although EV below PV also shows the project is behind schedule.
Note on D
Planned value plays no part in the manager’s reasoning; the comparison made is actual cost against the total budget.
Card 09 of 45Agile fit & frameworks
Halfway through a two-week sprint, a regulated customer contacts the Product Owner with a new mandatory reporting requirement. The developers are confident it is too large to finish before the sprint ends without dropping committed work. What should happen to this new requirement?
Note on A
Overtime to squeeze in unplanned work is unsustainable and undermines the plan the developers committed to.
Note on B
Cancelling a sprint is for when the Sprint Goal becomes obsolete; a new requirement that can be ordered for a coming sprint does not justify it.
Note on C
Correct: New work goes to the Product Backlog, where the Product Owner orders it against existing items for a future sprint while the current Sprint Goal stays protected.
Note on D
Adding a large item mid-sprint without dropping work breaks the team’s commitment and puts the Sprint Goal at risk.
Card 10 of 45Iterations & backlog
A project team is using an adaptive, iterative delivery approach with two-week iterations and a prioritized backlog. Which control mechanism is used in this adaptive environment?
Note on A
Correct: In adaptive delivery, control comes from frequent inspection: sprint reviews and acceptance of each increment show real progress and steer the next iteration.
Note on B
Baseline comparison and formal change requests are predictive controls; adaptive teams handle change through backlog ordering.
Note on C
Earned value against a cost baseline is a predictive measure and is not the main control loop in iterative delivery.
Note on D
Stage gates tied to an approved scope baseline belong to predictive life cycles, not two-week iterations with a living backlog.
Done 0
What to do with a miss
Step 1
Read the note on your pick
It names the idea you reached for instead. On this exam that is usually a neighboring term from the same domain, a sponsor’s job credited to the project manager, say.
Step 2
Then read the key’s note
The two notes together give you the line between the ideas, which is what the next card on the topic will test.
Step 3
Open the topic page
The topic table at the finish links each lane to its page in the CAPM study guide, where the ideas come before the cards.
Step 4
Come back with a clock
Once a rerun shows no weak lane, sit the timed CAPM mock exam, or pace the remaining weeks with the CAPM study plan.
The board and the real exam
Are these PMI’s questions?
No. The cards were written for study and none comes from a live exam or from PMI. Each was answered blind, from the stem and options alone, before its key was compared, and cards where the two disagreed were replaced.
Will the real CAPM look like this board?
Only in part. The exam mixes multiple choice with drag-and-drop matching, hot spot items, short animations and comic strips, and candidates testing online see comic strips but no animations (CAPM content outline, checked October 30, 2026). A web board can reproduce the multiple choice. The length, the clock and the break are set out on the questions and time page.
Is the mix weighted like the exam?
By domain, yes: the board lands close to PMI’s 36, 17, 20 and 27 percent. PMI publishes weights for the four domains only, with no split by topic and none between predictive and agile items, so each topic page names the domain it belongs to.